Hive beats ROC cut-off on 123MW

Hive Energy completed six UK solar farms totalling 123MW ahead of the 31 March deadline for Renewable Obligation Certificates. The facilities are the 14.5MW Poulshot, 27MW Lynt and 13.5MW Roundponds in Wiltshire, the 13.1MW Folly in Hertfordshire, the 6.4MW Goldenhill in Pembrokeshire and the 49MW Southwick in Hampshire. The land […]

To-the-point: Hive Energy completes 123 MW of solar parks in UK

seenews

April 1 (SeeNews) – UK-based firm Hive Energy on Wednesday said it has completed 123.5 MW of solar parks on time to qualify for 1.4 Renewable Obligation Certificates (ROCs) per MWh. The project developer has initiated commercial operations at six new plants, the two largest being the 49-MW Southwick solar […]